WIRELESS FLEXIBLE PERSONALIZED COMMUNICATIONS           COST 259
Work Plan
 
  
Last updated : 1999-06-19
Workplan for 1999
 

(1) ACTION PROFILE

Action no.: 259

Action title: Wireless Flexible Personalised Communications

MC Chairperson: Luis M. Correia

Commencement date: April 1997

Scheduled completion date: April 2000

Extension request: ----

Number of COST countries currently participating: 18

Number of COST country entities (institutes, etc.) currently participating: 0

Number of other entities (institutes, etc.) currently participating: 0

Estimated total Action cost for year 1999: 179 kECU

Number of Management Committee Members: 80

Titles of any Action Working Groups (with current number of members per group):

WG.1 Radio Systems Aspects - 20

WG.2 Propagation and Antennas - 40

WG.3 Network Aspects - 20



(2) ACTION MANAGEMENT

Management Committee Meetings (scheduled or expected)

Nº1

Title:

Location: Thessaloniki, Greece

Date: Jan. 1999

Nº2

Title:

Location: Vienna, Austria

Date: Apr. 1999

Nº3

Title:

Location: Amsterdam, The Netherlands

Date: Sep. 1999

Other meetings:

Nº1

Title: Subgroup on Directional Channel Models

Location: to be defined in the Sep. 1998 meeting

Date: to be defined in the Sep. 1998 meeting

Nº2

Title: Subgroup on Standard Scenarios for Frequency Planning

Location: to be defined in the Sep. 1998 meeting

Date: to be defined in the Sep. 1998 meeting

 



(3) OBJECTIVES FOR YEAR (to be achieved during year)

(4) ACTIVITIES PLANNED FOR YEAR (including short-term scientific missions)

Nº1: exchange of researchers within the partner institutions, for increasing the mutual collaboration

Nº2: exchange of measured data within the partner institutions, for models validation

Nº3: continuous update of the www site of the Action, and maintenance of the various email reflectors for the participants in the Action and in the Working Groups

Nº4: organisation of special sessions of the Action in major international conferences on mobile communications, namely VTC’99 Fall

Nº5: increase of collaboration with other COST Actions

Nº6: increase of collaboration with projects in the ACTS, SMT and ESPRIT frameworks
 



(5) OUTPUTS PLANNED FOR YEAR (including final reports, technical documents, publications, and other forms of output)

Nº1: Second Year Report

Nº2: 2nd COST 259 Workshop Proceedings

Nº3: "www page", with links to the main related sites



(6) WORKSHOPS AND SEMINARS

Nº1

Title: 2nd COST 259 Workshop

Purpose
: To put together experts in the area of adaptive (smart) array antennas for mobile communications, and to present the results of the second year.
Output expected: Workshop Proceedings
Origin of participants: Members and experts of the Action, invited speakers from organisations outside the Action, and participants from European industries

Number of participants: 120
Location: Vienna, Austria
Date: Apr. 1999

Nº2

Title:
Purpose:
Output expected:
Origin of participants:
Number of participants:
Location:
Date


Estimated budget

 

(1) SECRETARIAT

15 kECU

Total support required for item 15 kECU

(2) PUBLICATIONS (not including final report)

8 kECU

Total support required for item 8 kECU

(3) WORKSHOPS AND SEMINARS

28 kECU

Total support required for item 14 kECU

(4) MEETINGS

N?1: 32 kECU

N?2: 32 kECU

N?3: 32 kECU

Total support required for item 96 kECU

(5) SHORT-TERM SCIENTIFIC MISSIONS

Subgroups meetings 20 kECU

Exchanges 20 kECU

Action representation 6 kECU

Total support required for item 46 kECU

(6) GRAND TOTAL

Total support required for item 179 kECU